The Bathroom this Weekend or Else!!!

We started the bathroom Jan 21st and today is March 4th. It has been functioning as a bathroom since the 25th I need this room to be finished. the is the goal room this weekend. The walls have the final coat of mud on. The final sand can be done when the mud is dry. Then it can be primed than painted and all of the lighting can be reinstalled. That leaves the molding, window and door frame to be put up and painted. Can it be done? I hope so. Oh and then I can decorate. It is our only themed room... London is the theme. This is the shower curtain...

Finished Kitchen....

Well I am calling it done. I am sure things will change over time but for now we are done. Look a finished kitchen. Interior Temp New Sill Cool Faucet Stuff Newish art? OK an old painting cut up and framed. Same doggie door cleaned up. I know but it is funny. He Smiles.

I am Just so excited!!!

The kitchen is 97% done and should be complete this week. Tile finished and grouted and now all we need is the molding finished and the final coat of paint. Just a reminder of how bad it was... I will post the final pictures when complete.

We Are Getting closer

We had a productive weekend. Doug And Stephen got the roof finished. No leaks so far. Shane has a Shower and the backsplash in the kitchen is almost done. Ignore the mess it is hard living in a construction zone. Just needs grout. Stephen did a lovely job creating my new window sill. New molding around the windows and doors in kitchen just need the baseboards and cabinet kick-plates installed and the final coat of paint and the kitchen will be done. See I told you Shane has a shower. We have a sink too. Look accent tiles. List of things needed to be done in the bathroom. Door wall still needs Sheetrock. Tape and mud the walls. Paint walls. Install chair molding, crown molding and baseboards. Complete tile to crown molding. And the heat lamp needs to be installed. Wiring still needs to be finished

Bathroom Progress Slow and Steady

So our 4 days off to do the bathroom was not enough. We have one of the three fixtures working but there is a floor and we do have the trailer. *Day 1: Gut the room. Remove cast iron piping. Find out the floor was not stable. Doug and Stephen repair the floor. *Day 2: Plumbing installed and the floor gets tiled. *Day 3: Tub gets fixed in place. *Day 4: Shane's Birthday. Trying to rest but obsessing and the walls start coming down and start getting replaced. *Day 5: We have a toilet. Indoor plumbing is the way to go really. *Day 6: Floor finally grouted. Gray grout with white tiles. I do think this floor is what most people remove from their bathrooms but I like it.

Oh The bathroom...

So we have started the bathroom. It is gutted and we found our first problem. As problems go it really isn't that bad. The people who built the house didn't care that the floor could fall in around the toilet. No floor support, and the last time the toilet was replaced the toilet wasn't bolted down so it leaked... MMM delicious. Here are a couple of before and during shots. hoping buy Monday to show you a more or less finished bathroom. Before Toilet rot... The new plumbing getting installed is cool. It it tubing that feels like a hula hoop. Vent hole no support from below...Danger What I am envisioning...We will see how close we get.

The Kitchen is more than just a dream.

So it is slow work but it does look good when it gets finished. We are still not real sure on the backsplash hence the lack of one. It is a little more country than I like but we are on a budget. Painting is cheaper than replacement. The same with the butcher block counter. Ooooo shiny knobs. Creating Shane's hot drink station. Going to add a mug shelf. We are probably going to do a white subway tile back splash.